The Project Scope
Kiewit contacted ACQUIP to ascertain the vertical alignment of eleven vertical pumps at the world’s largest pump station in New Orleans, LA. None of the pumps could operate for an extended period of time. At least eight of the pumps had to be operating in 33 days.
acquip performance
ACQUIP Alignment Engineers were on site the same day to assess the situation. We quickly adapted our current bracketing to access the large location bores of the vertical pumps. In addition we designed and manufactured additional bracketing specific to the application. We called in added resources to staff the project 24 hours a day and provide up to the minute updates on progress and support needs.
results
ACQUIP quickly and accurately performed the pump alignment of the bores so the pumps could be reinstalled within specification. Eight of the pumps were operating 5 days before the deadline. The pump station was running on time to prevent the city from flooding in the event of a hurricane.
For more information about our alignment services contact us +1 305 538 7101 or email us at info@acquip.com.
Kiewit services and company names are trademarks™ or registered® trademarks of their respective holders. Use of them does not imply any affiliation with or endorsement by them. Kiewit is a trademark of kiewit Corporation.